
Consider the following work breakdown structure:
What is the estimated expected (mean) time for activity Y?
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer:
Verified
Q96: A project is represented by the following
Q97: Consider the following work breakdown structure:
Q98: Consider the following work breakdown structure:
Q99: Consider the following work breakdown structure:
Q100: Consider the following work breakdown structure:
Q102: Which of the following is not characteristic
Q103: Which of the following is not an
Q106: Consider the following work breakdown structure:
Q108: Activity J has a duration of 7
Q118: If an activity is determined to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents