
Consider the following work breakdown structure: 
What is the estimated expected (mean) time for project completion?
A) 135 days
B) 145 days
C) 170 days
D) 180 days
E) 255 days
Correct Answer:
Verified
Q102: Which of the following is not characteristic
Q103: Which of the following is not an
Q106: Consider the following work breakdown structure:
Q108: Activity J has a duration of 7
Q109: Consider the following work breakdown structure:
Q110: Consider the following work breakdown structure:
Q111: Consider the following work breakdown structure:
Q112: Consider the following work breakdown structure:
Q115: Which of the following leads to simulation
Q118: If an activity is determined to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents