Which of the following leads to simulation being a useful tool with uncertain activity times?
A) paths that are not independent
B) networks with each activity on only one path
C) activity times that cannot be crashed
D) noncritical paths that have no variability
E) critical paths with activities with deterministic time estimates
Correct Answer:
Verified
Q108: Activity J has a duration of 7
Q109: Consider the following work breakdown structure:
Q110: In which phase of the project life
Q111: Which decision in project management has typical
Q112: Which decision in project management has typical
Q113: Consider the following work breakdown structure:
Q114: Consider the following work breakdown structure:
Q116: All of the following are areas of
Q117: Which phase of the project life cycle
Q118: If an activity is determined to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents