Solved

Brown's Construction Co Agreed to Renovate a Lecture Hall at Moosehead

Question 18

True/False

Brown's Construction Co agreed to renovate a lecture hall at Moosehead University.The contract required the work to be completed between July 1 and September 1 so that classes would not be disrupted.The contract also stated that Brown's Construction would be required to pay the university $10 000 for each week that the project ran over schedule.That provision was intended to allow Moosehead to rent other premises for the purpose of holding classes off-campus if Brown's Construction failed to perform on time.The amount of $10 000 per week was the parties' genuine estimate of the cost of leasing lecture space off-campus.In fact, the renovations were finished six weeks late.Because of an unexpected downturn in the economy, however, the university only had to pay a total of $20 000 to hold classes off-campus during the delay.Brown's Construction nevertheless may be required to pay $60 000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents