A critical path refers to:
A) a sequence of task activities whose order and durations indirectly affect the completion date of a project.
B) a sequence of task activities whose order and durations directly affect the completion date of a project.
C) a sequence of task activities whose order must be performed in parallel.
D) a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.
E) none of the above.
Correct Answer:
Verified
Q62: Which of the following states correctly the
Q63: The third phase of the project management
Q64: Changes to the baseline project plan might
Q65: Ensuring that all contractual terms of the
Q66: The responsibility for keeping all team members
Q68: Realistic time refers to:
A) the maximum period
Q69: What would be the estimated time for
Q70: Which of the following occurs during project
Q71: Pessimistic time refers to:
A) the maximum period
Q72: Which of the following states correctly the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents