Which of the following is true regarding Gantt chart construction?
A) Squares are used to represent activities.
B) To construct the Gantt chart, a horizontal bar is drawn for each activity that reflects its sequence and duration.
C) To show precedence relationships, arrows are used to connect the nodes.
D) Arrows are used to reflect the sequence of activities.
E) Ellipses are used to represent activities.
Correct Answer:
Verified
Q61: What would be the estimated time for
Q65: Ensuring that all contractual terms of the
Q67: A critical path refers to:
A) a sequence
Q68: Realistic time refers to:
A) the maximum period
Q69: What would be the estimated time for
Q73: Determining the strengths and weaknesses of project
Q74: Optimistic time refers to:
A) the maximum period
Q76: Any person, group of people, piece of
Q77: The final phase of the project management
Q88: The amount of time that an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents