Based on the optimistic, realistic, and pessimistic time estimates provided, determine the expected time.(Estimates are based on weeks.)
-Optimistic = 4; realistic = 6; pessimistic = 10
A) 1 week
B) 6 weeks
C) 5 weeks
D) 6.33 weeks
E) 3 weeks
Correct Answer:
Verified