An action item list is
A) a list of topics to be covered during a meeting that shows the running time allocated to and the person(s) responsible for leading the discussion for each topic.
B) a chart that demonstrates how a set of tasks for a project can be sequentially and concurrently completed by specified times.
C) an aid to implementing a marketing plan consisting of four columns: (1) the task,(2) the person responsible for completing that task,(3) the date to finish the task,and (4) what is to be delivered.
D) a tool that shows the relationships through time of the various program tasks,which involves: (1) identifying the main tasks;(2) determining the time required to complete each task;(3) arranging the activities to meet the deadline;and (4) assigning people the responsibilities to complete each task.
E) a statistical tool,used in project management,that is designed to analyze and represent the tasks involved in completing a given project.
Correct Answer:
Verified
Q107: Edwin H. Land, former CEO of Polaroid,
Q121: Organizational groupings in which a unit is
Q126: Those in staff positions have the authority
Q128: People in _ positions have the authority
Q130: A company that uses an organizational structure
Q146: An action item list is an aid
Q147: An aid to implementing a marketing plan
Q152: A list of topics to be covered
Q154: Developing a program schedule involves which of
Q156: Line positions refers to
A)managers who have the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents