AFB Systems is considering a new marketing campaign that will require the addition of a new computer programmer and new software.The programmer will occupy an office in AFB's current building and will be paid $8,000 per month.The software license costs $1,000 per month.The rent for the building is $4,000 per month.AFB's computer system is always on,so running the new software will not change the current monthly electric bill of $900.The incremental expenses for the new marketing campaign are
A) $13,900 per month.
B) $9,000 per month.
C) $13,000 per month.
D) $8,000 per month.
Correct Answer:
Verified
Q34: Sunk costs are
A) recoverable.
B) incremental.
C) not relevant
Q35: In general,a project's free cash flows will
Q36: An opportunity cost is a relevant incremental
Q37: Tillamook Farms invests in a new kind
Q38: Which of the following expenses associated with
Q40: What is an incremental cash flow? What
Q41: If the increase in net working capital
Q42: Cash flows associated with a project's termination
Q43: Terminal cash flows are always positive because
Q44: The initial outlay includes the cost of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents