Estimated (remaining cost) to completion (ETC) is calculated as…
A) (BAC - EV) /CPI
B) (BAC - EV) /SPI
C) (BAC + EV) /CPI
D) (BAC + EV) /SPI
E) (BAC - AC) /CPI
Correct Answer:
Verified