In the terminology of the Critical Path Method,a critical path is which of the following?
A) the sequence of activities that is expected to take the longest time to complete
B) the composite of tasks in a project that have predecessors; the predecessors are critical to the accomplishment of subsequent tasks
C) a path that includes two or more activities that must be performed simultaneously, and therefore poses complex coordination problems
D) the series of tasks that is expected to take the shortest time to complete
Correct Answer:
Verified
Q103: The process used to prepare meals in
Q104: Production of a standardized product would most
Q105: Which of the following is a quality
Q106: Gantt charts and the Critical Path Method
Q107: Which of the following is/are reprogrammable machines
Q109: Which of the following is/are the replacement
Q110: Anne Miles owns a small business that
Q111: Billie Raney is in charge of a
Q111: As a general location factor, which of
Q112: What type of firm holds inventories of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents