Planning Processes

Question 39

Multiple Choice

Planning processes:


A) Signal the beginning of the project or phase.
B) Requires an organization to make a commitment of time and resources.
C) Are part of the project management processes and ITPM phases.
D) supports planning of the entire project and each individual phase
E) none of these

Correct Answer:

verifed