An activity being analyzed under PERT was judged to most likely have a duration of 40 days.When considering the time it would take to complete the activity if every relevant factor went well, it was estimated to be able to be doable in 20 days and even under the worst case imaginable, the task would be take 50 days.The estimates PERT duration of that activity is:
A) 36.67 days
B) 38.33 days
C) 37.50 days
D) 28.33 days
E) 32.67 days
Correct Answer:
Verified
Q17: The critical path is the longest path
Q18: The project budget is determined by the
Q19: An over allocated resource would arise when
Q20: PERT was developed in the 1950s to
Q21: The kick-off meeting brings closure to the
Q23: The tool most closely associated with activity
Q24: A kick-off meeting is often held to
Q25: The technique used to find the sequence
Q26: Starting the next task before the first
Q27: The Critical Path is:
A) the longest path
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents