Under the Precedence Diagramming Method, the situation which occurs when two activities can start at different times, have different durations, but are planned to be competed at the same time is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Correct Answer:
Verified
Q39: Under the Precedence Diagramming Method, the situation
Q40: _ provide valuable information about the logical
Q41: Time and effort needed to gather experience
Q42: Waiting to leave your shift until another
Q43: Rolling wave planning is:
A) developing a large
Q45: Costs incurred prior to the current project
Q46: Once the project schedule and project budget
Q47: Critical Chain Project Management (CCPM) is based
Q48: Define predecessor, successor, and parallel activities.Give a
Q49: Scheduling other projects so that resources may
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents