Three Team Members Are Given the Task of Estimating Activity

Question 69

Essay

Three team members are given the task of estimating activity durations.Mr.Optimist estimates the activity to take 2 days to complete.Ms.Pessimist estimates the activity to take 5 days.Mrs.Realist claims that the most likely estimate is 4 days.What should their PERT analysis assign as an expected duration for the activity and what are the benefits and implications of deploying this tool?