Barring a change in project scope and given a Cost Performance Index (CPI) that is less than 1, the most reasonable inference to draw is that:
A) The project will likely finish earlier than planned.
B) The project will likely finish later than planned.
C) The project will likely cost more than planned.
D) The project will likely cost less than planned.
E) The project will likely be on time and on budget.
Correct Answer:
Verified
Q31: If you hired a consulting firm to
Q32: The budgeted cost of work scheduled for
Q33: Cost Variance (CV) is _
A) how much
Q34: Earned Value tells us _
A) how much
Q35: Expected Time to Completion (ETC) is _
A)
Q37: A metric that provides an estimate for
Q38: Actual Cost (AC) is _
A) how much
Q39: If we know the Actual Cost of
Q40: Estimate at Completion (EAC) is _
A) how
Q41: Describe how the SPI and CPI can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents