The most important requirement for project closure under normal circumstances is:
A) completing the project on time.
B) completing the project on or under budget.
C) redeploying team members successfully to other projects.
D) following the project methodology.
E) obtaining the project sponsor's acceptance of the project.
Correct Answer:
Verified
Q43: Organizing and archiving of all project deliverables
Q44: In the final analysis, project success is
Q45: Demonstrating that all project deliverables have been
Q46: What is implementation?
Q47: The final project report should include:
A) Project
Q49: Describe the three approaches to implementing an
Q50: What are the advantages and disadvantages of
Q51: _ may sometimes occur weeks or months
Q52: What are the advantages and disadvantages of
Q53: What are the advantages and disadvantages of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents