Jessica hires ChromaLite Builders Corp.to construct a house.The contract specifies that grade A+ carpeting is to be installed on the entire second floor.ChromaLite Builders accidentally installs grade A carpeting instead.Few people,except for carpeting experts,can tell the difference.Jessica,however,refuses to pay for the construction citing that ChromaLite Builders has breached the contract.Which of the following statements is true in this scenario?
A) The courts are likely to consider ChromaLite Builders's performance as complete performance, and Jessica will have to pay the full amount to ChromaLite Builders.
B) Jessica can claim a breach of contract and refuse to pay ChromaLite Builders for the construction of the house.
C) The courts are likely to consider ChromaLite Builders's performance as a substantial performance, and Jessica would be entitled to monetary damages.
D) Jessica has materially breached the contract by refusing to pay ChromaLite Builders; hence, she cannot sue ChromaLite Builders for the use of low-grade carpeting.
E) The courts are likely to declare that ChromaLite Builders has materially breached the contract and will ask Jessica to pay exactly half the cost originally mentioned in the contract.
Correct Answer:
Verified
Q49: If a contract contains a condition precedent
Q50: _ is a middle ground between full
Q51: An exception to the parol evidence rule
Q52: A condition subsequent in a contract
A) implies
Q53: In the context of performance,the benefit of
Q55: According to the Uniform Commercial Code,a _
Q56: An offer to perform an activity under
Q57: ToughBuilders Corp.,a construction company,finishes the construction of
Q58: Which of the following is the key
Q59: Which of the following statements is true
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents