What is project slack?
A) The amount of time a non-critical task can be delayed without making the project late.
B) The amount of time the critical path of a project can be delayed without making the project late.
C) The amount of time an activity on the critical path can be delayed without making the project late.
D) The difference between how long the project would take if all tasks were completed based on their pessimistic versus optimistic time estimates.
E) None of the above.
Correct Answer:
Verified
Q6: The difference between LFT and EFT is
Q7: An event is a series of connected
Q13: A diagram of nodes connected by directional
Q15: Milestones are not depended upon the predecessor
Q26: The amount of time an activity can
Q33: The tasks of project planning, project budgeting,
Q38: For which purpose is simulation NOT used
Q39: What is it a milestone?
A) a significant
Q41: Why should we only draw the Gantt
Q44: The simulation approach is generally preferred over
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents