Which of the following linkages is used to start two or more activities at the same time?
A) finish-to-start
B) start-to-start
C) finish-to-finish
D) start-to-finish
E) They can all be used to start two or more activities at the same time.
Correct Answer:
Verified
Q54: Which of the following is typically used
Q62: Why is it necessary for the PM
Q69: Slack is calculated as?
A) LFT - EST
B)
Q72: The amount of time a noncritical task
Q77: A Term not used in the discussion
Q81: Technical dependencies on a project plan are
Q85: Contrast total slack and free slack.
Q95: What is the expected time to complete
Q105: Explain why the term critical path has
Q108: What is a merger and what problems