Which of the following was NOT listed in the text as a convention for estimating task progress?
A) 50% when task is started and another 50% when it is completed
B) 100 percent when task is completed and 0% before that
C) using the ratio of cost expended to total cost budgeted
D) using the ratio of time expended to the total time scheduled
E) all of the above were mentioned
Correct Answer:
Verified
Q29: According to the text, there is no
Q30: Which of the following is NOT an
Q31: Which of the following is NOT a
Q31: Weekly progress report meetings should be rarely
Q38: Exception reports are primarily intended for unexpected
Q40: Project review meetings are always important.
Q54: Which of the following is most closely
Q57: The plan-monitor-control cycle is best described as…
A)
Q63: Estimated (remaining cost) to completion (ETC) is
Q74: The cost/spending variance is calculated as…
A) AC
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents