Adding More People to a Delayed Systems Development Project Will

Question 77

Multiple Choice

Adding more people to a delayed systems development project will further delay the project because ________.


A) it is more difficult to schedule tasks
B) training new people slows down team members
C) it is more difficult to analyze the system requirements
D) it is more difficult to budget project costs

Correct Answer:

verifed

Verified