Solved

Brown's Construction Co Agreed to Renovate a Lecture Hall at Moosehead

Question 12

True/False

Brown's Construction Co agreed to renovate a lecture hall at Moosehead University.The contract required the work to be done between July 1 and September 1 so that classes would not be disrupted.The contract also stated that Brown's would be required to pay the university $10 000 per week for each week that the work ran over schedule.That part of the contract was intended to allow Moosehead to rent other premises for the purpose of holding class off-campus in the event of a delay as a reasonable pre-estimate of liquidated damages.In fact,the project was finished six weeks late.Because of an unexpected downturn in the economy,however,the university only had to pay a total of $20 000 to hold classes off-campus during the delay.Brown's Construction nevertheless may be required to pay $60 000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents