Teatro Restoration,Inc.,begins renovating an old theater for Urban Edge Productions,but after three months Teatro demands an extra $250,000. Urban Edge agrees to pay.
-Refer to Fact Pattern 12-4. If Teatro says it is asking for the extra $250,000 because it has encountered extraordinary unforeseen difficulties that will add consid-erable cost to the project,the agreement is
A) enforceable as the consideration is past.
B) enforceable because of unforeseen difficulties.
C) unenforceable as an illusory promise.
D) unenforceable due to the preexisting duty rule.
Correct Answer:
Verified
Q32: Valley Paragliders Association files a suit against
Q45: Frisco offers to buy a Gibson guitar
Q46: Sally contracts with Tasty Pizza Company to
Q47: Jenilee promises to pay Kyle $500 because
Q48: Teatro Restoration,Inc.,begins renovating an old theater for
Q49: Teatro Restoration,Inc.,begins renovating an old theater for
Q51: Under a contract with Valley Vineyard, Walsh
Q52: Digital Enterprise,Inc.,promises to pay its employees a
Q53: William buys Liz's house for $100,000,which is
Q55: D'Sean promises to pay his personal assistant
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents