Solved

A PERT Chart

Question 79

Multiple Choice

A PERT chart:


A) portrays a project as a network diagram consisting of numbered nodes that represent tasks.
B) is used to evaluate project risk and time.
C) displays a horizontal bar for each project task.
D) tracks progress of, and modifications to, project tasks.

Correct Answer:

verifed

Verified

Unlock this answer now