Which of the following statement(s) concerning probabilities of completion is/are incorrect?
A) Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B) The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C) The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D) The individual activity completion times must be normally distributed
Correct Answer:
Verified
Q1: The amount of flexibility the project manager
Q13: Which of the following project categories might
Q14: According to Goldratt,to complete a project on
Q15: When workers receive approval for a task
Q16: The amount of time a project manager
Q18: The set of all project activities graphically
Q19: Duration of critical path - path duration
Q20: Project charters should contain some level of
Q29: Three phenomena that tend to bias the
Q31: Using CPM,when activity times are not known
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents