In a PERT/CPM chart, each task has which of the following ____.
A) references to successor tasks
B) references to predecessor tasks
C) start day/date
D) resources allocated
Correct Answer:
Verified
Q9: A event is a recognizable reference point
Q10: Many project managers find _ charts more
Q11: When several tasks can start at the
Q12: A project manager's scheduling function _.
A)involves guiding,
Q13: A project manager's planning _.
A)involves guiding, supervising,
Q15: A _ path includes all tasks that
Q16: A(n) _ chart displays complex task patterns
Q17: In addition to tasks, every project has
Q18: PERT/CPM is called a(n) _ technique, because
Q19: The first step in the creation of