Shane contracts to build a garage for Bob for a price of $6,000.Because of an increase in the cost of labor and materials, Shane refuses to perform.Bob wants the garage, so he agrees to pay an additional $500.In this case:
A) Bob must pay the additional $500.
B) Shane has given no additional consideration, and under the common law he must perform at the agreed-upon original price.
C) the substitute agreement is an illusory contract.
D) the debt is a disputed one, and therefore Bob is obligated to pay the additional money.
Correct Answer:
Verified
Q48: Which of the following are the two
Q59: Andrew agrees to paint Rosalene's house for
Q63: Define legal detriment.
Q65: A bank robbery has occurred,and the banker's
Q69: There are certain transactions that are enforceable
Q70: Ron owes Matt an unsecured deposit of
Q71: Which of the following statements best describes
Q72: Roberto obtains an exclusive franchise to sell
Q74: Ken,a research chemist,has been promised a fellowship
Q81: Define a substituted contract and explain how
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents