In some situations,two activities are scheduled to be carried out in parallel and using the same scarce resource.If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously,then whichever of the two is given priority immediately lengthens the other activity's path but not its actual __________.
A) duration
B) slack
C) float
D) buffer
Correct Answer:
Verified
Q32: Which of the following describes a situation
Q33: Using the _ heuristic method,the project team
Q34: The methods to find an optimal solution
Q35: Because the project _ is the source
Q36: Assume two activities,printing and binding.Printing is a
Q38: The tasks that logically precede a particular
Q39: Three important parameters used to assess the
Q40: _ aims to minimize the period-by-period variations
Q41: Discuss the advantages obtained from resource leveling.
Q42: Describe the basic procedure for resource leveling.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents