Solved

James Ford an Architect Charges $150 Per Hour for His

Question 190

Multiple Choice
James Ford an architect charges $150 per hour for his time spent drawing blueprints for clients. His budgeted annual cost to run his office is $12,000 a year (rent and utilities) and he allocates these indirect costs based on direct labor hours. Ford predicts that he will work about 1,000 billable hours per year for his clients. Recently, Ford completed a set of blueprints for a garage for one of his clients and involving 30 hours of work, How much indirect costs should ford allocate to the garage blueprints job when considering how much to charge his client and cover his costs?

James Ford an architect charges $150 per hour for his time spent drawing blueprints for clients. His budgeted annual cost to run his office is $12,000 a year (rent and utilities) and he allocates these indirect costs based on direct labor hours. Ford predicts that he will work about 1,000 billable hours per year for his clients. Recently, Ford completed a set of blueprints for a garage for one of his clients and involving 30 hours of work, How much indirect costs should ford allocate to the garage blueprints job when considering how much to charge his client and cover his costs?


A) $450
B) $810
C) $360
D) $330

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents