Which of the Following Is the Correct Formula for the Materials

Question 74

Multiple Choice
Which of the following is the correct formula for the materials price variance?
A) (Actual price of input - Budgeted price of input) x Budgeted quantity of input
B) (Actual quantity of input used - Budgeted quantity of input allowed for actual output) x Budgeted price of input
C) (Actual price of input - Budgeted price of input) x Actual quantity of input
D) (Actual quantity of input used - Budgeted quantity of input allowed for actual output) x Actual price of input

Which of the following is the correct formula for the materials price variance?


A) (Actual price of input - Budgeted price of input) x Budgeted quantity of input
B) (Actual quantity of input used - Budgeted quantity of input allowed for actual output) x Budgeted price of input
C) (Actual price of input - Budgeted price of input) x Actual quantity of input
D) (Actual quantity of input used - Budgeted quantity of input allowed for actual output) x Actual price of input

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents