A company has a policy "investigate all variances exceeding $3,000 or 15% of the budgeted cost, whichever is lower." There is a variance of $2,000 in repair and maintenance costs of $12,000. What does the company do in the given situation?
A) It should be ignored as it is less than $3,000.
B) It deserves more attention as it is more than 15% of total repair cost.
C) It should be considered an in-control occurrence.
D) It should be investigated as all variances are equally important.
Correct Answer:
Verified
Q149: Effectiveness is _.
A) the relative amount of
Q150: Cost variances should be investigated _.
A) when
Q151: A percentage of products started and completed
Q152: A variance within an acceptable range is
Q153: In variance analysis, if any single performance
Q155: The emphasis on variance analysis and its
Q156: Which of the following statements is true
Q157: If management experiences an unfavorable direct materials
Q158: The term for understanding why actual performance
Q159: Nonfinancial performance measures _.
A) are usually used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents