The main groupings for the work in a WBS chart are listed in the second tier of boxes,called level ____.
A) 0
B) 1
C) 2
D) 3
Correct Answer:
Verified
Q48: Duration estimates are provided as a _
Q49: In an AOA network diagram,_ occur when
Q50: Project management software uses the _ format
Q51: In an AOA network diagram,a(n)_ occurs when
Q52: After defining project activities,the next step in
Q54: The project team begins to develop a
Q55: The project manager should work with his
Q56: What is the PERT weighted average based
Q57: In the context of a network diagram,a
Q58: Tasks in a WBS that are decomposed