Question 57

Multiple Choice

Risk reassessment,risk audits,variance and trend analysis,technical performance measurements,reserve analysis,and status meetings or periodic risk reviews are all tools and techniques for performing ____ monitoring and control.


A) scope
B) risk
C) cost
D) quality

Correct Answer: