A(n)_________,which Is a Project Management Technique,can Be Established Using the Critical

Question 64

Multiple Choice

A(n) _________,which is a project management technique,can be established using the critical path to list the completion time of a project on the x-axis and all the activities on the y-axis.


A) work breakdown structure
B) event chain diagram
C) Gantt chart
D) risk register

Correct Answer:

verifed

Verified