A subdivision is planned for forty houses,each with its own in-ground swimming pool.A contractor estimates it will take him 30 hours to build the first pool and that there is a 90% learning curve associated with this process.
-How long will it take to build all of the pools?
A) 17.1 hours
B) 642.75
C) 796.3 hours
D) 1200.0 hours
Correct Answer:
Verified
Q19: Virtual supply chains have the advantage of
Q19: The break-even formula Q22: What is the break even point for Q22: A company with fixed costs of $10,000 Q24: Consider the system composed of four processes Q25: A lead capacity strategy has the advantage Q26: Jimbo Elrod has obtained fixed and variable Q27: Which of the following statements about learning Q28: The average waiting time on a Thursday Q52: A firm is more likely to develop![]()