The earliest finish time is calculated by adding the activity's duration to the predecessor's earliest finish time.
Correct Answer:
Verified
Q42: The longest path in a network from
Q43: An activity's duration added to its earliest
Q44: The earliest finish time of an activity
Q45: The university president concocts a thirteen-step
Q46: A hatmaker, fresh off a very
Q48: A hatmaker, fresh off a very
Q49: A forward pass through a network is
Q50: Complete this table containing earliest and
Q51: Given the earliest and latest finish
Q52: For critical path activities, slack is equal