The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.The fixed cost for being on site is $450.What is the lowest total completion cost for the project?
A) $10,600
B) $11,000
C) $11,400
D) $12,000
Correct Answer:
Verified