If a Liquidated Damages Clause Demands an Unusually Large Sum

Question 46

Multiple Choice

If a liquidated damages clause demands an unusually large sum that is not related to reasonably-anticipated actual damages, the clause will be held to be void as a(n) :


A) penalty.
B) unliquidated damages clause.
C) extortion
D) blackmail

Correct Answer: