A cutting tool has a lifetime that is normally distributed with an average life of 400 hours and a standard deviation of 50 hours.Present policy is preventive maintenance which requires changing all cutting tools at the end of each month.Current operations are two shifts per day and 7 working hours per shift.At 20 days per month,each cutting tool is in use 280 hours per month.(All cutting tools that fail are simply shut down until the end of the month sweep).The variable costs of replacement under the current policy are $8 per tool plus installation labor of $6 per tool.There are 40 tools in use.
-Management is considering a change in policy that would change cutting tools every two months instead.Cutting tools that fail are replaced immediately,but the replacement labor is $16 per tool because each replacement is a special order.At the sweep,all tools,even recent replacements,are replaced.What is the annual cost of this proposed policy?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q97: Orders that produce learning about a new
Q98: _ is credited has having developed benchmarking
Q99: Bar codes and _ are popular ways
Q100: Process charts use _ for storage.
A)triangles
B)circles
C)squares
D)arrows
Q101: A cutting tool has a lifetime that
Q103: Discuss the two ways process redesign can
Q104: Why is the idea of reengineering appealing?
Q105: Why are job shops generally back-logged?
Q106: How can process charts be used to
Q107: A cutting tool has a lifetime that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents