Constant Matching of Estimated and Actual Times

Question 70

Multiple Choice

Constant matching of estimated and actual times


A) shows whether the backlog is increasing,decreasing,or staying about the same.
B) reveals the knowledge and skill of the schedulers.
C) highlights bottlenecks and problem areas.
D) reveals scheduled work not completed.

Correct Answer: