Solved

Determine Line Efficiency and Relate It to the Balance Delay

Question 106

Essay

Determine line efficiency and relate it to the balance delay measure (given in Equation 17-4) for the following conditions: Total work content is 3 hours;there are 180 stations operating with a cycle time of one minute.Compare the results and meanings of d and L.

Correct Answer:

verifed

Verified

L = Line efficiency = (3)(60)/(180)(1) =...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents