Solved

If a Liquidated Damages Clause Demands an Unusually Large Sum

Question 44

Multiple Choice

If a liquidated damages clause demands an unusually large sum that is not related to reasonably-anticipated actual damages,the clause will be held to be void as a(n) :


A) penalty.
B) unliquidated damages clause.
C) Extortion
D) Blackmail

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents