Scope creep refers to:
A) the tendency for project scope to keep getting bigger and bigger.
B) subdividing project deliverables into smaller pieces.
C) the approved project scope statement and its associated WBS.
D) a task at the lowest level of the WBS.
Correct Answer:
Verified