The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.
A) early finish date
B) late finish date
C) late start date
D) early start date
Correct Answer:
Verified
Q63: After reviewing the project management plan, project
Q67: A(n) _ is a schematic display of
Q71: In a(n) _ relationship, the "from" activity
Q72: In a network diagram, a(n) _ is
Q76: A draft schedule for a project is
Q79: The activity list should include the _,
Q80: In a project schedule, the variable that
Q89: What are milestones? Describe.
Q91: Duration estimates can be provided as a
Q92: A(n) _ determines the early start and