Solved

Which of the Following Is True of Earned Value

Question 78

Multiple Choice

Which of the following is true of earned value?


A) It is the actual cost plus the planned cost. 
B) It is based solely on the total cost estimate to be spent on an activity. 
C) It is an estimate of the value of the physical work actually completed. 
D) It is also known as the planned value.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents