_____ Involves Numerically Estimating the Effects of Risks on Project

Question 27

Multiple Choice

_____ involves numerically estimating the effects of risks on project objectives.


A) Performing qualitative risk analysis
B) Planning risk responses  
C) Identifying risks
D) Performing quantitative risk analysis

Correct Answer:

verifed

Verified