Which of the following best explains a situation where a contractor agrees to work based on a fixed sum plus extra payments based upon superior performance?
A) Fixed sum contract.
B) Fixed price contract.
C) Contractor commitment.
D) Fixed price plus incentive fee contract.
Correct Answer: