In the Key Elements of the Contracting Process Which Element

Question 50

Multiple Choice

In the key elements of the contracting process which element comes before testing and delivery and after subcontracting and procurement? 


A)  Basic design and engineering. 
B)  Project execution. 
C)  Detailed project engineering and planning. 
D)  Claims.

Correct Answer: