Which of the following best explains 'assembly to order (ATO) '?
A) Only raw materials and components are kept in stock.
B) All activities are planned based upon customer order.
C) There is no stock held at all.
D) Manufacture takes place based on forecasts and final assembly takes place based on customer orders.
Correct Answer:
Verified
Q16: Which of the following is not a
Q17: Which of the following is a characteristic
Q18: Which of the following best explains the
Q19: Which of the following best explains the
Q20: Which of the following is a characteristic
Q22: Which of the following is not a
Q23: Which of the following best explains 'Camp's
Q24: Which of the following best explains 'just-in-time
Q25: Which of the following best explains 'pay
Q26: Which of the following best explains 'make
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents